Guide to private construction contracts, serious defects (art. 1669 Civil Code) and pre-trial technical assessment in Italy

12 Novembre 2026

Cracking walls, water infiltration, systems that do not work: if the work was carried out under a construction contract, Italian law protects the client with deadlines and remedies that differ according to how serious the defect is.

1. Non-conformities and defects (arts. 1667-1668 of the Civil Code)

The contractor is liable for non-conformities and defects in the work. The client must give notice within sixty days of discovery and take action within two years of delivery. The client can ask for the defects to be remedied at the contractor’s expense or for a price reduction and, if the defects make the work wholly unfit for its purpose, for termination of the contract, as well as damages.

2. Serious defects: ten-year liability (art. 1669 of the Civil Code)

For buildings and other immovable works intended by nature to last a long time, if within ten years of completion the work collapses in whole or in part, or shows an evident danger of collapse or serious defects, the contractor is liable. The client must give notice within one year of discovery and take action within one year of the notice. This usually covers defects that significantly affect functionality or habitability, such as widespread infiltration or subsidence. Liability may also extend to the designer and the works supervisor, according to their tasks.

3. The conciliatory pre-trial technical assessment (art. 696-bis of the Code of Civil Procedure)

Before starting a lawsuit, the court can be asked to appoint an expert also aimed at settling the dispute. The expert ascertains and quantifies defects and damage and attempts conciliation. If the parties agree, the record has the force of an enforceable title. The procedure does not require proof of urgency.

4. What to do straight away

  • photograph and document the defects with a certain date;
  • send written notice (PEC or registered letter) to the contractor and the other professionals;
  • keep the contract, specifications, bill of quantities, minutes, invoices and test certificates;
  • do not carry out permanent repairs before the site has been inspected, so as not to lose the evidence.

Case studies

Case studies described in general terms: names, places and details do not refer to real people or files.

Infiltration discovered late

The situation: a renovated condominium shows damp patches in the fourth year; only in the sixth year, with a thermographic survey, is it discovered that the vapour barrier under the external insulation is missing.

A possible route: the contractor argues that notice was late. The defence argues that the one-year period of art. 1669 runs from full knowledge of the seriousness of the defect and its cause, not from the first patches; the defect appeared within ten years and the action is brought within one year of the notice.

A dispute settled through the conciliatory assessment

The situation: eight months after delivery a client complains of infiltration from the terrace; the contractor denies the defects and demands payment of the last progress invoice.

A possible route: an application under art. 696-bis c.p.c. with a party expert report. The court-appointed expert ascertains errors in laying the waterproofing membrane and attempts conciliation: the parties offset the repair costs against the outstanding balance, and the record is given the force of an enforceable title.

How the firm can help

Every case depends on the documents and the dates. The firm examines your situation and, before the engagement, gives you a written quote under art. 13 of Law 247/2012.

Request an online consultation WhatsApp Call 347 5264190

Official sources: Normattiva – arts. 1667, 1668 and 1669 of the Civil Code, art. 696-bis of the Code of Civil Procedure, Law 247/2012. This guide is for general information and does not replace legal advice on a specific case. Avv. Renato Giuseppe Fiorentino, lawyer registered with the Naples Bar · Studio Legale Fiorentino, Piazza Giovanni Bovio 22, 80133 Naples · Tel. and WhatsApp 347 5264190 · By appointment in Naples, Rome and Bari, and by online consultation from all over Italy.

Come può seguirti l’avv. Fiorentino

Lo studio assiste privati e imprese a Napoli, Roma e Bari, e a distanza in tutta Italia. Prima dell’incarico ricevi un preventivo scritto (art. 13 L. 247/2012).

Richiedi una consulenza online
WhatsApp 347 5264190 · Chiama 347 5264190 · Scrivi all’avvocato

Sedi su appuntamento: Napoli, P.zza Giovanni Bovio 22 · Napoli, Via Monte di Dio 14 · Roma, Viale Giorgio Ribotta 21 · Bari, Via Domenico Morea 38 · P.IVA 06116130722